COMMITTEE MEETING MINUTES – 09/07/2024



Meeting: MHSBM
Date: July 9, 2024
Time: 15:00 – 16:30
Location: Medrock Offices
Attendance
- Joe Pilcher
- Gareth Jones
- John Canepa
- Jason Mesilo
- Pepe Figueredo
- Derek Sene (late to the meeting)
- Absent: John Collins, Johnny Buttiguieg
Agenda
- Opening Remarks
- Approval of Previous Minutes
- JBS Works Update
- Snagging Meeting
- Weight Test for Loose Block
- Engineering Report for Nissen Huts
- New Finger Pontoon
- Crane Cover
- Tender Documents Discussion
- Focus Camera Installation
- Meeting with Captain of the Port
- Meeting with Victor (Office Admin)
- Any Other Business (AOB)
- Closing Remarks
Minutes
1. Opening Remarks
- We are moving in the right direction and its good to see us all aligned on a common goal.
2. Approval of Previous Minutes
- The minutes of the previous meeting have been approved.
3. JBS Works Update
- JBS works have been finished, and the invoice has been issued for payment, totaling £35,554.03.
4. Snagging Meeting
- The snagging meeting was held, and all is complete and fine.
5. Weight Test for Loose Block
- The weight test indicated no impact with the loose block. We just need the green light to place the block back in its place and begin operating the crane.
- GJBS will place the block back at some point, even if they need to work around us.
6. Engineering Report for Nissen Huts
- The engineering report indicates a cost of £47,900 to fix the Nissen huts for use as storage. It should then be approved as a permanent structure.
- A vote was held to proceed:
- Joe: Yes
- Pepe: No
- Everyone else: Yes
7. New Finger Pontoon
- We need a finger pontoon to make lifting the boats easier. The cost is £23,000, including transport and fitting.
- John Canepa got the first quote; Derek Sene will get the second quote.
- The preliminary cost of £23,000 has been approved.
8. Crane Cover
- The crane cover spend has been halted.
9. Tender Documents Discussion
- Tenders are all out, and responses have been received.
- Gareth will post the Pier Master job role on Facebook.
10. Focus Camera Installation
- Focus has finished installing cameras and linking systems. We will have a meeting with Daniel Bosano regarding a maintenance contract.
11. Meeting with Captain of the Port
- The meeting went well. We are liaising with the dock controllers as a working group to clear the pontoon names and boat numbers lists as currently its quite a mess.
- We will review the arrears process and enforcement.
- We need to discuss empty berths with the Minister, as the Captain says it has stopped at the ministerial level.
- There are people living in boats in the marina on pontoon K (K21 and K23). This needs to be addressed urgently as it is not allowed in the constitution.
12. Meeting with Victor (Office Admin)
- The meeting with Victor went well. He was pressed to chase outstanding fees, which he did. He will try to be more proactive.
13. Any Other Business (AOB)
- Jason, Acting Captain, has reviewed all the pontoons (A-L) and noted there are 84 eyebolts.
- The mess on the pontoons needs to be addressed.
- The marina will be fixing and repairing; we will subcontract this work.
- Discussion about WiFi in the marina, which should cost around £2,000. A vote was held: 2 for, 2 against.
Action Items
- Place the loose block back in its place and begin operating the crane once the green light is given.
- Approve and proceed with the engineering report for the Nissen huts as a permanent structure.
- Obtain a second quote for the new finger pontoon.
- Finalize and approve the tender documents for Cleaners, Administrative Officer, Security Officers, Marina Operative, and Pier Master.
- Gareth to post the Pier Master job role on Facebook.
- Arrange a meeting with Daniel Bosano to discuss the maintenance contract for the camera system.
- Liaise with dock controllers to clear the pontoon names and boat numbers lists.
- Review the arrears process and enforcement.
- Discuss empty berths with the Minister.
- Address the issue of people living in boats in the marina on pontoon K (K21 and K23).
- Monitor and follow up on Victor’s progress in chasing outstanding fees.
- Revisit the discussion about WiFi installation in the marina in future meetings.
- Subcontract the work for fixing and repairing the mess on the pontoons.
Next Meeting
- Date: August 6, 2024
- Time: 15:00
- Location: Medroock Offices